2. Align with maintenance strategiesEP 2009-9009
Restricted
25
2.4Set up FSRFacility Status Reporting (FSR) is the Global standard tool to support the management of the SCEs and it has three main functions. Visualisation (consolidated picture) of the status of the
CMMS work orders and notifications and related deviations by barrier/SCE group, at any level within the FSR Asset hierarchy.
2. Communication - FSR monitors those items that require action, and notifies the relevant parties by email. A formal and auditable Deviation Management System. Appendix 4 contains a listing of the key configuration items which are needed to deploy FSR.
Safety Critical Element Management ManualEP Restricted Work Preparation, Scheduling and Execution Process
Guide (EP 2006-5445).
• Corrective Maintenance Prioritisation Tool (CMPT).
• Manual of Permitted Operations (MOPO)
(EP 2005-0300-SP-04).
3. Execute performance assurance activitiesThe SCE performance assurance tasks are carried out in the field, the results are recorded and assessed for conformance with the performance standard acceptance criteria and any follow on corrective work is identified. This section describes the performance assurance steps that are in addition to the normal maintenance work preparation, scheduling
and execution activities, which are detailed in the Work
Preparation, Scheduling and Execution Process Guide
(EP The end result of the activities in this section is the identification of SCEs meeting their performance standards acceptance criteria follow on corrective work for SCEs which do not meet their performance
standards acceptance criteria, which includes agreed priority and Latest Allowed Finish Date
(LAFD)
• SCE performance assurance task backlog deviations needed.