Date
|
23rd May 2016
|
Division / Programme
|
BBC Childrens / Justin’s House: Series 4
|
Location
|
HQ3 Studios, MediaCityUK, Salford
|
Name of Set / Area of works
|
HQ3 Studio Floor & Tech Store, plus Loading Bay @ Studios, MediaCityUK
Production Office: 1st Floor Bridge House, MediaCityUK
|
Proposed Start Date
|
|
|
Lighting
|
Set
|
Mon
|
23rd May
|
|
|
Tue
|
24th May
|
|
|
Wed
|
25th May
|
|
|
Thu
|
26th May
|
Overnight Overhead Rig
|
|
Fri
|
27th May
|
|
Steelwork/Flat Construction
|
Sat
|
28th May
|
Set Specials/LEDs
|
Construction/Dressing
|
Sun
|
29th May
|
Rigging Cabling/Under Set Lights/Wires
|
Cut Traps/Dressing
|
Mon
|
30th May
|
FIRST REHEARSAL ON SET
|
Reh
|
Tue
|
31st May
|
|
Reh
|
Wed
|
1st June
|
Programming/Sound Rig
|
Reh & Light
|
Thu
|
2nd June
|
Camera Rig
|
RX 1 & 2
|
Fri
|
3rd June
|
|
Read through 5&6
Reh 3 & 4
|
|
Estimated Finish Date
|
Mon
|
1st August
|
|
Reh
|
Tue
|
2nd August
|
|
Reh
|
Wed
|
3rd August
|
|
Reh
|
Thu
|
4th August
|
|
RX 17 & 18
|
Fri
|
5th August
|
|
RX 19 & 20
|
Sat
|
6th August
|
Derig lights from set
Strike moving Lights Overhead
|
Remove Flats then Steel construction.
Load & Clear
|
Sun
|
7th August
|
|
|
Mon
|
8th August
|
|
|
Tue
|
9th August
|
|
|
|