Table 7 to Table 11 provide the inputs and outputs for the various life cycle phases. The inputs and outputs provided, represent the more important (significant) ones for the identification of impacts.
1.9.1Construction Phase: Input/Output Diagramme
Table 7: Construction Phase: Input/Output Parameters (Duration About 24 Months)
The site for the proposed Plant is located on a previously disturbed area some 400 meters south east of Koeberg Nuclear Power Station. The site falls within the outer security fence of the Koeberg NPS. No pristine fynbos will be disturbed and proper access roads as well as security fencing and access control facilities exist:
INPUT OUTPUT
DIRECT
-
Dewatering
-
Construction, and
-
Sewage
DIRECT
-
Building materials and construction machinery
-
Capital
-
Jobs
-
Construction
-
Component manufacture
-
Plant and equipment
-
Housing
-
Professional, commercial and social services (e.g. medical, schools, banking, postal, telecoms, shops, potable water, emergency services, road etc.)
-
Transmission upgrades
-
Noise from construction activities
-
Emissions/dust
-
Stimulation of local/regional economy (temporary)
-
Communicable disease
-
Increased traffic
-
Complete module
CONSTRUCTION OF MODULE
1.9.2Commissioning Phase : Input/Output Diagramme
Table 8: Commissioning Phase Input/Output Parameters (Duration ± 6 Months)
A two stages commissioning procedure will be followed, namely:
-
Cold Commissioning : The Plant will be run without any nuclear fuel. This procedure will test the integrity and functionality of the
of the various structures, system and components to the extent for positive non-power conditions.
-
Hot Commissioning : The Plant is loaded with nuclear fuel and the nuclear reaction is initiated. Thereafter the Plant is monitored
in various modes, to assess the systems, and components and techno-economics.
INPUT OUTPUT
COLD COMMISSIONING
Note: Plant is run without nuclear fuel
-
Hot (Thermal) effluent
-
Domestic effluent
-
Solid waste (domestic)
-
Nitrogen Gas
-
Energy (Electricity)
-
Sea Water (Cooling)
-
Potable Water
-
Emissions (Nitrogen)
COMMISSIONING PHASE
(about 6 to 9 months)
-
Helium Gas
-
Energy (Nuclear fuel)
-
Graphite spheres
-
Sea Water
-
Potable Water
-
Labour
-
Helium emissions
-
Radioactive emissions,
-
Effluent and solid waste
-
Radiological
-
Non-radiological
-
Thermal
HOT COMMISSIONING
1.9.3Operational Phase : Input/Output Diagramme
Table 9: Operational Phase Input/Output Parameters (Duration 40 Years)
The in- and outputs of this phase resembles that of the Hot Commissioning phase except for the quantum of in- and outputs
INPUT OPERATIONAL/MAINTENANCE PHASE OUTPUT
-
Nuclear fuel
-
Graphite spheres
-
Helium gas
-
Electricity (Sales)
-
Spent fuel
-
Emissions (helium)
-
Radioactive waste
-
Gaseous
-
Liquid
-
Solid (filters, clothing)
OPERATION
(about 40 years)
-
Solid
-
Liquid
-
Redundant parts/Components
-
Data on radiological effects on staff and environment
OPERATIONAL
&
MAINTENANCE PHASE
-
Finance
-
Institutional Support e.g. NNR, Eskom, local authorities, contractors, provincial authorities (schools, health, education, etc) professional services
-
Replacement parts
-
Non-Radiological
-
Radiological (e.g. filters)
-
Graphite column of the reactor
-
MONITORING OF ENVIRONMENT & STAFF
MAINTENANCE
(about 1 week per year of operation)
1.9.4 Decommissioning Phase: Input/Output Diagramme
Table 10: Decommissioning Phase : Input/Output Parameters (Duration About 1 Year)
-
Reduced services are provided during the decommissioning phase
-
Detailed plans and options are developed for the dismantling of the Plant
INPUT DECOMMISSIONING PHASE OUTPUT
-
Clean-up of MPS & Reactor
-
Spent fuel (final load out)
-
Radiological waste - Solid
-
(LLRW & ILRW) - Liquid
-
Data on environmental quality
-
Retrenchment/pensioned/re-employed staff
-
Redundant equipment/components/parts
DECOMMISSIONING PHASE
(about 1 year)
Note: The Design of the Plant is such that it can safely remain in idle state for a prolonged period while radioactive wastes decay
LLRW = Low Level Radioactive Waste
ILRW = Intermediate Level Radioactive Waste
1.9.5Dismantling Phase : Input/Output Diagramme
Table 11: Dismantling Phase : Input/Output Parameters (Duration 1 – 2 Years)
-
This phase will entail the removal of all equipment (radiological and non-radiological)
-
This phase resembles the Construction Phase in the reverse e.g. equipment is removed, irradiated parts are decontaminated and building structures are demolished as needed and disposed of.
INPUT DISMANTLING PHASE OUTPUT
-
Radiological (LLRW & ILRW) and construction waste
-
Data on environmental quality
DISMANTLING PHASE
(actual time for this phase may range from 1 – 2 years)
Note : The spent fuel components can be maintained for a prolonged period after decommissioning, even if the final deposition High Level Radioactive Waste (HLRW) repository is not available.
Share with your friends: |