1. General 8
2. Definitions 11
3. Overview of the Plan Development Process 20
Generalized Plan Development Process Flow Diagram 22
4. Planning, Programming and Scheduling 24
Project Identification 24
Programming 25
Management of Long Range Projects 25
Schedule Development 25
Monitoring Schedules 26
Project Manager Responsibilities 26
Resource Planning 27
District Preconstruction Review Meeting 27
Revision of Project Schedules 27
Let Status Review 27
HOLD and SHELF Status 28
5. Concept Development Stage 30
General 30
Objectives 30
Projects Not Requiring Concept Meeting or Concept Report 30
Initial Concept Development and Initial Concept Meeting 31
Concept Development Considerations 33
Concept Team Meeting 35
Concept Report 37
Concept Report for Minor Projects 37
Concept Report Processing for Reports Prepared by GDOT 37
Concept Report Processing for Reports Prepared by Local Governments 38
Concept Report Updating 39
Concept Report Approval 39
Approved Concept Report Distribution 39
Revised Concept Reports 39
Concept Reports For Interstate ITS Projects 40
Preliminary Concept Reports for Hardship and Protective Buying 41
Updated Cost Estimates 41
Value Engineering Studies at Concept Stage 42
6. Preliminary Design 44
Project Data Design Book 44
Environmental Process – Federal Aid 44
Environmental Studies 45
Phase 1 – Information Gathering 45
Phase 2 – Analysis of Social, Economic and Environmental Data 46
Air Quality 46
Noise Impact Study 47
Farmland Study 47
Natural Resources Study 47
Cultural Resources Study 48
Phase 3 – Preparation of the Environmental Document 48
Phase 4 – Public Involvement 48
Outreach Programs 48
Informal Meetings 49
Pulic Information Open House 49
Opportunity for a Public Hearing Open House 50
Public Hearing Open House 51
Public Open House Notices 51
Public Information Meeting for Proposed Detours 53
Phase 5 – Final Alternate Selection Report 54
Environmental Reevaluation – Federal Aid 54
Environmental Process – State Funded Projects 55
Georgia Environmental Policy Act (GEPA) 55
Georgia Environmental Policy Act Reevaluation 56
Roadway Design Offices – Major Projects 56
Surveying and Mapping 57
Preliminary Design 58
Constructability Review in Preliminary Design 58
Value Engineering Study in Preliminary Design 60
Preliminary Right of Way Plans 61
Preliminary Field Plan Review 61
Roadway Design Offices – Minor Projects 63
Office of Bridge Design – Bridge and Retaining Wall Design 63
Office of Right of Way 64
Office of Utilities 65
Subsurface Utility Engineering(SUE) 65
Utility Relocation Plans and Agreements 65
Railroads 66
Office of Traffic Safety and Design 66
Office of Maintenance 68
Office of Transportation Data 68
7. Final Design 70
Location and Design Approval – Major Projects 70
Location and Design Approval – Minor Projects 71
Design Office – Major Projects 71
Design Office – Minor Projects 72
Final Right of Way Plans 72
Right of Way Revisions 73
Right of Way Acquisition 73
Office of Utilities 73
Utility Relocation Plans 73
Utility Agreements 73
Railroads 74
Office of Traffic Safety and Design 74
Final Field Plan Review - Major Projects 74
Final Field Plan Review - Minor Projects 76
Submission of Plans for Letting 76
Plans and Specifications Revisions after Submission for Letting 78
Right of Way Certification 78
Utility Certification 78
Environmental Certification 78
8. Design Guideline Variances 81
Design Exception 81
Design Variance 82
9. Construction 85
Construction Authorization 85
Transition Conference 85
Revisions to Projects Between Authorization and Letting 86
Revisions During Construction 86
Review of Completed Project 86
10. Project Management System 87
Pre-Construction Project Team 87
TPro’s Benefits to Project Managers 88
Project Manager’s Responsibilities in TPro Schedule Maintenance 88
TPro’s Benefits to the Department’s Construction Work Program 89
Appendix 92
Appendix A. Certification Acceptance Agreement(CA) 92
Appendix B. Need and Purpose Statement Requirements 100
Appendix C. Concept Reports 102
Definitions, Procedures, Federal Agencies Listing 102
Example Concept Report Transmittal Letter 104
Example Concept Report 105
Example Revised Concept Report Transmittal Letter 112
Example Revised Concept Report 114
Appendix D. Final Alternate Selection Report Example 116
Appendix E. Location and Design Approval 118
Requirements for Advertising 118
Example Request for Location and Design Approval 119
Example Notice of Location and Design Approval 121
Appendix F. Field Plan Review 122
Request for a Preliminary Field Plan Review 122
Final Field Plan Review 125
Appendix G. Procedures To Prepare Noise Impact Assessments 127
Appendix H. Ecology Requirements for Project Area Study 129
Possible Threatened and Endangered Species 129
Consideration for Stream Impacts 130
Consideration for Wetland Impacts 131
Appendix I. Historic and Archaeological Resource Requirements 133
Historic Resources Surveys 133
Background Research 133
Survey Methodology/Field Survey 133
Survey Criteria for Historic Resources Surveys 133
Archaeological Resources Surveys 136
Background Literature Research 136
Intensive Archaeological Survey 137
Data Analysis 137
Survey Objectives 138
Appendix J. Minor and Non-Land-Disturbing Projects 142
Appendix K. Design Exception or Variance Report Example 145
Appendix L. Procedures for Determining Bridge Size at Stream Crossings 147
Appendix M. FHWA Exemptions from USCG Permit Requirements 149
Appendix N. Useful References 151
Appendix O. Procedure for Securing Consultant Services 161
Appendix P. Plan Revision Procedures 167
Appendix Q. Detour Report and Notice 173
Appendix R. Project Framework Agreements (PFA) 177
Appendix S. Erosion, Sedimentation, and Pollution Control Plan 178
Appendix T. Final Plans Transmittal Letter 182
Appendix U. Traffic Engineering Report 184
Appendix V. Highway Systems Administrative Review 191
Index 201
This document sets forth the current procedures and steps necessary for the Georgia Department of Transportation (GDOT) to administer Federal-Aid projects in accordance with the policies and objectives of Titles 23, 40, and 42 United States Code, and to administer State-Aid projects to fulfill the policies and objectives of Title 32, Official Code of Georgia Annotated. The document outlines the current process of project development from project identification through construction award.