Eliminating the water loss in Elbistan, which is as high as 60% in the present situation, and ensuring economical use of water sources,
-
Providing water service with equal rates to people by resolving operation problems in the network
-
By preventing permeability of the water supply lines, preventing mixing from outside and construct a healthier network
-
Avoiding frequent failures in the existing network and reduction of risk caused by pipe repair works to city life and to other infrastructure facilities,
-
Replacement of pipes having risky material like asbestos
-
Decrease of water costs by avoiding water losses and providing inexpensive, high-quality and continuous use of water for the city people,
-
Decrease of operation and maintenance costs by reducing excavation and repair works caused by network failures,
-
Contributing protection of public health with continuous and healthy water service,
-
Increasing life quality of people and to make a basic step for urban development of Elbistan.
ENVIRONMENTAL MANAGEMENT PLAN ENVIRONMENTAL RISK FACTORS
Excavation and transportation works in construction activities are the main factors causing environmental and social risks. Information about excavation and transportation are given under the following headings. Recommendations to manage and avoid the risk factors are given in other sections.
Excavation
Excavation rates depending on the ground type and excavation type for the plants to be newly constructed are given in Table 3 .3.
Table 3.3 Excavation Rates Prescribed for New Plants
|
Ground Type
|
Excavation Type
|
Location
|
Soil
%
|
Pick Rock
%
|
Soft Rock
%
|
Hard Rock
%
|
Mechanical
%
|
Manual
%
|
Caisson Well Collection Rooms at Groundwater extraction Locations
|
50
|
50
|
--
|
--
|
90
|
10
|
TMY1 and TMY2 Pumping Stations at Groundwater extraction Locations
|
100
|
--
|
--
|
--
|
90
|
10
|
DY1 Reservoir
|
--
|
--
|
80
|
20
|
90
|
10
|
DY3, DY4 Reservoirs and TMY3 and TMY4 Pumping Stations
|
--
|
30
|
70
|
--
|
90
|
10
|
Rising Mains and Network
|
70
|
15
|
10
|
5
|
90
|
10
|
Transportation
Transportation operations may be taken on two basis. Firstly, transportation of material from other cities to Elbistan and secondly, transportation of material brought to Elbistan from temporary storage area to the construction site. Possibilities within the closer areas will be primarily evaluated during the process of material supply and transfer. Prior supply alternatives for these materials are stated below.
-
Sand and gravel: To be provided from Municipality Stone & Sand Quarry at 7 km away.
-
Stone: To be brought from the Municipality Stone Quarry at 7 km away.
-
Cement: To be brought from the Gaziantep Cement Factory 245 km away from Elbistan.
-
Reinforced Concrete Steel: To be provided from İskenderun Iron and Steel Co. 450 km away from Elbistan.
-
PVC Pipe: To be provided from Elazığ Plastic Pipe Factory 220 km away from Elbistan.
-
HDPE Pipe: To be provided from Kayseri Akın Plastic Pipe Factory 290 km away from Elbistan.
-
Brick: To be provided from Kahramanmaraş Brick Factory 165 km away from Elbistan.
-
Steel Pipe: To be brought from the Istanbul Pendik Ümran Pipe Factory 1040 km away from Elbistan.
All the companies supplying materials have valid licences and permits (including environmental permits where necessary)
In Elbistan, materials will be carried to regions where new reservoirs, pumping station, rising mains and networks lines shown in Figure 2 .4 are located. Effects of transportation in Elbistan will be determining for the urban life. Measures and improvement suggestions about possible impacts in transportation operations are given in the following sections.