5 Current Status of Noise Environment Status, Impact Assessment and Mitigation Measures 5.1 Monitor and Evaluation on Current Noise Status 5.1.1 Monitoring method and sampling locations
The monitoring method shall follow the “Standard of environmental noise of urban area (GB/T14623-93)”. In principle, the measurement shall be done in the day when there is no rain and the wind velocity is less than 5.5m/s.
In accordance with the “Technical Guidelines for Noise Impact Assessment (HJ/T2.4-1995)” and “Specifications for Environment Impact Assessment of Highway (JTJ005-96)” while in combination with characteristics of the project, sampling locations for monitoring the current noise status of the project shall follow the principles below:
The sampling points shall cover the entire range for assessment as much as possible. However, the focus shall be the areas that are sensitive against the noise.
Set sampling points near the flyover and in sites where are sensitive against the noise.
As per principles above, 5 sampling points for noise are set within noise assessment range of the Nanjiang Binlu Project, 7 for the 3rd Ring Road Project (Phase II) and 4 for Kuiqi Bridge, i.e.:
(1) Sampling points for Nanjiang Binlu: 1# Puxiazhou; 2# Fanchuanpu Catholic Church; 3# Annan Assembly Hall; 4# Yinghua English School; 5# Residential Area K1+620. Please refer to Fig. 5.1-1 for details.
(2) Sampling points for the Phase-II Project of the Third Ring Road : 1# Shangqi Primary School; 2# Yangxia Village; 3# Wushan Primary School; 4# Pukou Xiazhou Village; 5# Fujian College of Information and Technology; 6# Duyuan Village; 7# Linpu Primary School. Please refer to Fig. 5.1-1 for details.
(3) Sampling points for Kuiqi Bridge: 1# Kuiqi Village; 2# Kuiqi Primary School; 3# Waitang Village; 4# Shaoqi Village
Please refer to Fig. 5.1-1 for details of above sampling points.
(3) Sampling points for Kuiqi Bridge: 1# Kuiqi Village; 2# Kuiqi Primary School; 3# Waitang Village; 4# Shaoqi Village. Please refer to Fig. 5.1-2 for details of above sampling points.
5.1.2 Monitoring time
Each sampling points shall be monitored for 2 days, with noise sampled in the daytime and nighttime everyday.
5.1.3 Standard for current noise environment assessment
Equivalent continuous A-weighted noise pressure level and noise level are selected for noise assessment.
Assessment by equivalent continuous noise level Leq is:
Thereinto: T ---- Measuring time;
L(t) ---- Instantaneous noise level at time t.
For background noise of the current environment, class 2 and 4 of the “Standard of environmental noise of urban area (GB3096-93)” are adopted. Please refer to Table 5.1-1 for details.
Table 5.1-1 Standard of Environmental Noise of UrbanArea (Unit: dB(A)
Class
|
Daytime
|
Nighttime
|
2
|
60
|
50
|
4
|
70
|
55
| 5.1.4 Monitored result of current noise environment and assessment
Please refer to Table 5.1-2 ~ Table 5.1-5 for monitored results of current noise environment
Table 0 7 Noise Monitored at Boundary of the Phase-II Project of the Third Ring Road of Fuzhou City, Feb. 19
Sampling Point
|
1
|
2
|
3
|
4
|
Time
|
Daytime
|
Nighttime
|
Daytime
|
Nighttime
|
Daytime
|
Nighttime
|
Daytime
|
Nighttime
|
Noise Value(LAeq,dB)
|
51.6
|
42.5
|
51.8
|
42.6
|
46.0
|
42.1
|
52.1
|
43.2
|
Orientation of Sampling Location
|
Yangqi Primary School
|
Yangxia Village
|
Wushan Primary School
|
Pukou Xiazhou Village
|
Table 5.2-2 Noise Monitored at Boundary of the Phase-II Project of the Third Ring Road of Fuzhou City, Feb. 19 (To be continued)
Sampling Point
|
5
|
6
|
7
|
Time
|
Daytime
|
Nighttime
|
Daytime
|
Nighttime
|
Daytime
|
Nighttime
|
Noise Value(LAeq,dB)
|
56.8
|
43.0
|
57.6
|
42.7
|
51.3
|
43.2
|
Orientation of Sampling Location
|
Fujian College of Information and Technology
|
Duyuan Village
|
Linpu Primary School
|
Table 5.1-3 Noise Monitored at Boundary of the Phase-II Project of the Third Ring Road of Fuzhou City, Feb. 20
Sampling Point
|
1
|
2
|
3
|
4
|
Time
|
Daytime
|
Nighttime
|
Daytime
|
Nighttime
|
Daytime
|
Nighttime
|
Daytime
|
Nighttime
|
Noise Value(LAeq,dB)
|
52.3
|
42.3
|
52.1
|
42.2
|
47.1
|
42.4
|
51.6
|
42.8
|
Orientation of Sampling Location
|
Yangqi Primary School
|
Yangxia Village
|
Wushan Primary School
|
Pukou Xiazhou Village
|
Table 5.2-3 Noise Monitored at Boundary of the Phase-II Project of the Third Ring Road of Fuzhou City, Feb. 20 (To Continue)
Sampling Point
|
5
|
6
|
7
|
Time
|
Daytime
|
Nighttime
|
Daytime
|
Nighttime
|
Daytime
|
Nighttime
|
Noise Value(LAeq,dB)
|
54.3
|
42.7
|
55.7
|
42.5
|
51.8
|
42.8
|
Orientation of Sampling Location
|
Fujian College of Information and Technology
|
Duyuan Village
|
Linpu Primary School
|
Table 5.1-4 Noise Monitored at Boundary of the Nanjiang Binlu of Fuzhou City, Feb. 19
Sampling Point
|
8
|
9
|
10
|
11
|
12
|
Time
|
Daytime
|
Nighttime
|
Daytime
|
Nighttime
|
Daytime
|
Nighttime
|
Daytime
|
Nighttime
|
Daytime
|
Nighttime
|
Noise Value(LAeq,dB)
|
54.9
|
42.5
|
53.8
|
41.8
|
57.9
|
45.6
|
64.0
|
45.8
|
67.8
|
48.8
|
Orientation of Sampling Location
|
Puxia Village
|
Fanchuanpu Catholic Church
|
Annan Assembly Hall
|
Yinghua English School
|
Residential Area K1+620
|
Table 5.1-5 Noise Monitored at Boundary of the Nanjiang Binlu of Fuzhou City, Feb. 20
Sampling Point
|
8
|
9
|
10
|
11
|
12
|
Time
|
Daytime
|
Nighttime
|
Daytime
|
Nighttime
|
Daytime
|
Nighttime
|
Daytime
|
Nighttime
|
Daytime
|
Nighttime
|
Noise Value(LAeq,dB)
|
55.2
|
42.3
|
54.3
|
42.0
|
57.6
|
46.7
|
58.6
|
46.9
|
67.2
|
47.7
|
Orientation of Sampling Location
|
Puxia Village
|
Fanchuanpu Catholic Church
|
Annan Assembly Hall
|
Yinghua English School
|
Residential Area K1+620
|
Viewing from monitored results shown in Table 5.1-2 to Table 5.1-5, the LAeq value daytime of the Phase-II Project of the Third Ring Road is (46.0~57.6) dB, which meets Class 2 standard given in “Standard of environmental noise of urban area (GB3096-93)”, and the LAeq value nighttime of the Phase-II Project of the Third Ring Road is (42.1~43.2) dB, which meets Class 1 standard given in “Standard of environmental noise of urban area (GB3096-93); the LAeq value daytime of the Nanjiang Binlu is (53.8~67.8) dB, which meets Class 4 standard given in “Standard of environmental noise of urban area (GB3096-93)”; and the LAeq value nighttime of the Phase-II Project of the Third Ring Road is (41.8~48.8) dB, which meets Class 2 standard given in “Standard of environmental noise of urban area (GB3096-93).
Share with your friends: |