The assessment scope of the surface water of the airport drainage project is Tashui Stream: the stormwater outfall of the airport extends to the Xinjiang Reach, approximately 9600m in total length.
Zunqiao Water: the stormwater outfall of the airport extends to the Xinjiang Reach, approximately 12200m in total length.
Xingfu Water: the stormwater outfall of the airport extends to the Fengxi Reach, approximately 13200m in total length.
The assessment scope of the surface water of the Airport Avenue is the downstream reach of the sewage outfall of Xinjiang Sewage Treatment Plant.
The assessment scope of the Ground Water of the project is determined by taking Xinjiang as the boundary in the north and the west and taking the Ground Water watershed as the boundary in the south and the east.
The ecological assessment scope of the airport avenue is 300m at both sides of the proposed road centerline.
See Figure 1-5-1 for the assessment scope.
Off-site project
|
Evaluation scope
|
Ecological environment
|
Sound environment
|
Water environment
|
Ambient air
|
Social environment
|
Electromagnetic environment
|
Airport avenue project
|
The project has no spoil ground. Carry out investigation on the ecological environment of the proposed soil-taken field with its evaluation scope as the soil-taken field and its surrounding 300m area.
|
200m scope on both sides of centerline of proposed road
|
Downstream river section of pollution discharge of Xinjiang sewage treatment plant
|
200m scope on both sides of centerline of proposed road
|
Town region affected along road
|
|
Pipeline project
|
Project region planning scope, about 2km2.
|
Within the project region, the sensitive area is properly extened.
|
Downstream river section of pollution discharge of Xinjiang sewage treatment plant
|
Region of 1-2km extended outside the project region boundary
|
Town region affected along the line
|
|
Natural water replacement project of off-site drainage and around airport
|
200m belt-shaped region scope on both sides of pipelines
|
Construction site and 100m on both sides along line
|
Tashuixi: Airport rain discharge outlet to Xinjiang River with full length of 9600m;
Zunqiaoshui: Airport rain discharge outlet to Xinjiang River with full length of 12200m.
Xingfushui: Airport rain discharge outlet to Fengxi River with full length of 13200m.
|
Evaluation scope of sewage pipeline and rain pipeline is 200m on both sides along the line.
|
Town region affected along the sewage pipeline and rain pipeline
|
|
Reconstruction project of village road around airport
|
300m scope on both sides of road
|
200m scope along the road
|
Near project and the river and irrigation ditches it passes
|
200m scope along the road
|
Town region affected along the road
|
|
110kV Maozao Line relocation and modification project of Sanqingshan Airport
|
300m scope on both sides of transmission line corridor
|
30m Belt-shaped region on both sides of transmission line corridor
|
Surface water in 500m region along the line
|
30m Belt-shaped region on both sides of transmission line corridor
|
Town region affected along the line
|
Take the 30m belt-shaped region on both sides of transmission line corridor as evaluation scope of power frequency electromagnetic field; take 2000m belt-shaped region on both sides of transmission line corridor as radio interference evaluation scope (wit
|
110kV Wangzao Line relocation and modification project of Sanqingshan Airport
|
300m scope on both sides of transmission line corridor
|
30m Belt-shaped region on both sides of transmission line corridor
|
Surface water in 500m region along the line
|
30m Belt-shaped region on both sides of transmission line corridor
|
Town region affected along the line
|
Take the 30m belt-shaped region on both sides of transmission line corridor as evaluation scope of power frequency electromagnetic field; take 2000m belt-shaped region on both sides of transmission line corridor as radio interference evaluation scope (wit
|
10kV line newly constructed project from Maojialing to Airport
|
30m scope on both sides of transmission line corridor
|
30m Belt-shaped region on both sides of transmission line corridor
|
Surface water in 500m region along the line
|
30m Belt-shaped region on both sides of transmission line corridor
|
Town region affected along the line
|
|
10kV line newly constructed project from Zaotou to Airport
|
30m scope on both sides of transmission line corridor
|
30m Belt-shaped region on both sides of transmission line corridor
|
Surface water in 500m region along the line
|
30m Belt-shaped region on both sides of transmission line corridor
|
Town region affected along the line
|
|