Output 3: Institutions for planning and implementing service delivery at local level

 Services are being planned and implemented at the local level

Sub-output 3.1

Deliverable 1

2H 2012

Deliverable 2

1H 2013

Deliverable 3

1H 2013

Deliverable 4

1H 2013

Target

2H 2013

Completion of policy framework for strengthening planning and implementation of service delivery

(NPP sub-component 14, deliverable 14.1)

Guidance on formulation of PDPs and Provincial Budgets modified to ensure internal linkages and links to Provincial Strategic Plan

Guidance on provincial level planning and district level planning modified to ensure district-level planning inputs into provincial planning

1 workshop for each of the 34 provincial administrations on the revised planning system

Key service delivery Ministries develop and approve policies on delegation of responsibility

All provincial planning processes have been clearly linked with each other and with PSP, and the overall process is linked to the national budgeting process

IDLG FP

CLPD

IDLG FP

 CLPD

IDLG FP

 CLPD

IDLG FP

 CLPD

External FP

 MoF, M. Ec

External FP

 MRRD

External FP

 All relevant

External FP

 All relevant

Channel

 Procedure

Channel

 Procedure

Channel

 Capacity

Channel

 Procedure

Sub-output 3.2

Deliverable 1

1H 2013

Deliverable 2

2H 2013

Deliverable 3

1H 2014

Deliverable 4

1H 2014

Target

2H 2014

Implementation of improved planning practices

(NPP sub-component 14, deliverable 14.2)

2 workshops in each province that has not yet completed Provincial Strategic Plan to support completion of PSP

 1 workshop and 1 week of implementation before start of new budget planning calendar to ensure formulation of Provincial Annual Plan (based on PSP, DDP inputs, etc)

1 workshop and 1 week of implementation support for each PDC/PAA on coordinating implementation of provincial plan & budget

 1 workshop and 1 week of implementation support for each PC on oversight of provincial plan & budget

All 34 provinces have implemented the strengthened planning cycle

IDLG FP

CLPD

IDLG FP

CLPD

IDLG FP

 CLPD

IDLG FP

 GDLC

External FP

N/A

External FP

M. Economy

External FP

 M. Economy

External FP

 N/A

Channel

Support 

Channel

Support 

Channel

 Support

Channel

 Support

Sub-output 3.3

Deliverable 1

1H 2013

Deliverable 2

1H 2013

Deliverable 3

1H 2014

Deliverable 4




Target

1H 2014

 Implementation of agreed reforms to provincial budget planning

(NPP sub-component 3, deliverable 3.1)

Expanded set of provincial line departments and expanded set of national programmes included in provincial budget pilot in all 34 provinces

Further expanded set if provincial line departments and programmes under provincial budgeting, some O&M budgeted for at least one programme

All major sectors including at least 1 programme in provincial budgeting, some O&M budgeted in all programmes

 

All 34 provinces are conducting budget planning for activities in their provinces in the major service delivery sectors

IDLG FP

P&P 

IDLG FP

P&P 

IDLG FP

P&P 

IDLG FP

 

External FP

MoF

External FP

MoF

External FP

MoF

External FP

 

Channel

Budget 

Channel

Budget 

Channel

Budget 

Channel

 

Sub-output 3.4

Deliverable 1

2H 2012

Deliverable 2

2H 2013

Deliverable 3

2H 2014

Deliverable 4




Target

2H 2014

 Implementation of agreed reforms to provincial budget allocation

(NPP sub-component 3, deliverable 3.2)

1392 provincial budget ceilings in Education and Local Governance set on formula basis

1393 provincial budget ceilings in Health sector set on formula basis

1392 provincial budget ceilings in Roads sector set on formula basis




Provincial budget ceilings in education, health, roads and local governance are set using efficient, transparent and fair criteria

IDLG FP

P&P 

IDLG FP

P&P 

IDLG FP

P&P 

IDLG FP

 

External FP

MoF

External FP

MoF

External FP

MoF

External FP

 

Channel

Budget 

Channel

Budget 

Channel

Budget 

Channel

 

Sub-output 3.5

Deliverable 1

2H 2012

Deliverable 2

1H 2013

Deliverable 3

1H 2013

Deliverable 4

1H 2013

Target

2H 2013

Implementation of agreed reforms to provincial budget execution

(NPP sub-component 3, deliverable 3.3)

Ministries participating in provincial budgeting delegate increased procurement authority required for execution of expenditures planned for provincial budgeting

Ministries participating in provincial budgeting disseminate guidance to their line departments on procurement practices for spending planned under provincial budgeting, based on guidance provided by MoF

Procurement planning and management tools prepared and distributed to line departments of all ministries participating in provincial budgeting in all 34 provinces


1 workshop and 1 week of implementation support for participating line departments in all 34 provinces during procurement for 1392

All 34 provinces are implementing payments and procurements for the activities that they planned and which were subsequently approved in the budget cycle

IDLG FP

P&P 

IDLG FP

P&P 

IDLG FP

P&P 

IDLG FP

P&P 

External FP

MoF

External FP

MoF

External FP

MoF

External FP

MoF

Channel

Budget 

Channel

Budget 

Channel

Procedure

Channel

Support 



Output 4: Accountability at the Provincial level

 Provincial Councils have the information, capacity and relationships needed to make other provincial agencies accountable

Sub-output 4.1

Deliverable 1

2H 2012

Deliverable 2

2H 2013

Deliverable 3

1H 2014

Deliverable 4

1 H 2014

Target

2H 2014

Creation and dissemination of legal framework for accountability at provincial level

(NPP sub-component 2)

Provincial Councils Law (PCL) and Right to Information Law (RIL) submitted to Parliament

PCL and RIL enacted (NPP deliverable 2.3)

PCL and RIL disseminated to SNG stakeholders

1 workshop for provincial officials and 1 workshop for PC, media & civil society on PCL and RIL in each province

Legal basis for generation of accountability at provincial level exists, and all leadership, senior staff & technical staff of SNG units are aware of it and understand it

IDLG FP

 P&P

IDLG FP

 P&P

IDLG FP

 P&P

IDLG FP

 LCA




External FP

 MoJ

External FP

 Parliament

External FP

 MoJ

External FP

 N/A




Channel

 Legislation

Channel

 Legislation

Channel

 Legislation

Channel

 Support




Sub-output 4.2

Deliverable 1

1H 2013

Deliverable 2

2H 2013

Deliverable 3

1H 2014

Deliverable 4

1H 2014

Target

2H 2014

Improved access to and usage of performance information by Provincial Councils

Government formulates policy on generation and distribution of performance relevant information

Main service delivery ministries develop, approve and implement procedures on generation and distribution of performance information

 1 workshop & 1 week of implementation support for each PC, and 1 workshop & 1 week of implementation support for PGO & selected LMs, on interpretation of performance information

1 public event in each province to present and discuss new system of information generation and distribution

Provincial Councils and other provincial stakeholders in all 34 provinces have access to information on provincial development, service delivery and administrative decision-making, and are able to interpret and use it

IDLG FP

 P&P

IDLG FP

 P&P

IDLG FP

 GDLC

IDLG FP

 GDLC




External FP

 All relevant

External FP

 All relevant

External FP

 N/A

External FP

 N/A




Channel

 Procedure

Channel

 Procedure

Channel

 Support

Channel

 Support




Sub-output 4.3

Deliverable 1

1H 2013

Deliverable 2

2H 2013

Deliverable 3

1H 2014

Deliverable 4

1H 2014

Target

2H 2014

Establishment of clear, detailed and agreed norms for relationship between Provincial Councils and other provincial agencies


Agreement between IDLG and relevant Ministries on PC-Line Department Head interactions

Development of guidance on PG-PC interactions by IDLG; joint development of guidance on PLD-PC interactions by IDLG and relevant Ministries

 In all 34 provinces: dissemination of PGO-PC guidance to PGOs and PCs by IDLG: dissemination of PGO-PLD guidance by relevant parent agencies.

1 workshop for Governor and Line Department Heads in each province; 1 workshop for Provincial Council in each province 

Detailed norms for PC interaction with line departments and PGOs defined and communicated; good degree of compliance in all 34 provinces

IDLG FP

 P&P

IDLG FP

P&P 

IDLG FP

CLPD 

IDLG FP

CLPD 




External FP

 All relevant

External FP

All relevant

External FP

N/A 

External FP

All relevant




Channel

 Procedure

Channel

Procedure 

Channel

Support 

Channel

Support 




Sub-output 4.4

Deliverable 1

1H 2013

Deliverable 2

2H2013

Deliverable 3

2H 2013

Deliverable 4

1H 2014

Target

2H 2014

Creation of an effective Public Grievances system under the supervision of the Provincial Council

(NPP sub-component 21)

Design of Public Grievances system based on review and baseline exercise in all 34 provinces (NPP deliverable 21.1)

Staff and budget required to add Public Grievances management to PC office requested

Recruitment, deployment of equipment and workshop on Public Grievances system in all 34 provinces

Public announcement and public discussion of Grievances system in all 34 provinces (NPP deliverable 21.3)

All 34 Provincial Councils have access to a system for receiving, acting on and reporting back on the complaints of the provincial electorate

IDLG FP

GDLC 

IDLG FP

GDLC 

IDLG FP

GDLC 

IDLG FP

GDLC 




External FP




External FP




External FP




External FP







Channel

Budget 

Channel

Budget 

Channel

Budget 

Channel

Budget 




Sub-output 4.5

Deliverable 1

1H 2013

Deliverable 2

2H2013

Deliverable 3

2H 2013

Deliverable 4

1H 2014

Target

2H 2014

Improvement of Provincial Council access to resources and operational support

(NPP sub-component 19)

Procedure for planning of PC budget revised to allow PC planning of own budget

Activities planned by 34 PCs within ceiling, funded by mix of core & donor funds

IDLG budget with PC inputs approved

Execution of approved, PC planned budgets initiated (NPP deliverable 19.2)

Flows to all 34 Provincial Council offices are increased in size and planned with much greater input from PCs

IDLG FP

GDLC , Fin.

IDLG FP

GDLC, Fin.

IDLG FP

GDLC, Fin.

IDLG FP

GDLC, Fin.




External FP

MoF 

External FP

MoF 

External FP

MoF 

External FP

MoF 




Channel

Budget 

Channel

Budget 

Channel

Budget 

Channel

Budget 






Output 5: Municipal service delivery cycle

 Provincial municipalities are raising revenue and using it to deliver the services that people want in a way that is transparent and consistent with good governance

Sub-output 5.1

Deliverable 1

2H 2012

Deliverable 2

2H 2013

Deliverable 3

1H 2014

Deliverable 4

1H 2014

Target

2H 2014

Creation and dissemination of legislative framework for municipal governance

(NPP sub-component 2)

Municipalities Law (ML) submitted to Parliament

ML enacted (NPP deliverable 2.2)

ML disseminated to SNG stakeholders

1 workshop for municipal and provincial officials and 1 workshop for PC, media and civil society on ML

Legal basis for municipal governance exists, and all leadership, senior staff & technical staff of SNG units are aware of it and understand it

IDLG FP

GDMA

IDLG FP

GDMA

IDLG FP

GDMA

IDLG FP

GDMA

External FP

MoJ

External FP

Parliament

External FP

MoJ

External FP

N/A

Channel

Legislation

Channel

Legislation

Channel

Legislation

Channel

Support

Sub-output 5.2

Deliverable 1

2H 2012

Deliverable 2

1H 2013

Deliverable 3

1H 2013

Deliverable 4

2H 2013

Target

2H2013

Establishment of improved systems or municipal revenue collection

(NPP sub-component 17, deliverables 17.1-17.2)



Revenue Improvement Action Planning (RIAP) manual developed and approved 

Revenue Improvement Action Planning (RIAP) manual disseminated to all Provincial Municipalities, and workshop conducted in each municipality to review material

Revenue Administration information systems rolled out to all Provincial Municipalities

1 week of implementation on revenue improvement for revenue officials in all Provincial Municipalities

All 33 provincial municipalities have developed and are implementing Revenue Improvement Action Plans, and are collecting more revenue from a wider base as a result

IDLG FP

GDMA

IDLG FP

GDMA

IDLG FP

GDMA

IDLG FP

GDMA

External FP

N/A

External FP

N/A

External FP

 N/A

External FP

N/A

Channel

Procedure

Channel

Procedure

Channel

Investment

Channel

Support

Sub-output 5.3

Deliverable 1

2H 2012

Deliverable 2

1H 2013

Deliverable 3

1H 2013

Deliverable 4

2H 2013

Target

1H 2014

Establishment of improved systems or municipal financial management, execution and reporting

(NPP deliverable 17.3)

Financial Management manual develop and approved

Financial Management manual disseminated to all Provincial Municipalities, and workshop conducted in each municipality to review material 

Upgraded FMIS rolled out to all Provincial Municipalities

2 weeks of implementation of improved Financial Management for finance departments of all Provincial Municipalities

All 33 provincial municipalities pass financial audit without major issues, while increasing budget execution to over 75%

IDLG FP

GDMA

IDLG FP

GDMA

IDLG FP

GDMA

IDLG FP

GDMA

External FP

N/A

External FP

N/A

External FP

 N/A

External FP

N/A

Channel

Procedure

Channel

Procedure

Channel

Investment

Channel

Support

Sub-output 5.4

Deliverable 1

1H 2013

Deliverable 2

2H 2013

Deliverable 3

1H 2014

Deliverable 4

2H 2014

Target

1H 2015

Establishment of improved systems or planning, implementation and evaluation of municipal service delivery

2 planning workshops and 2 weeks of implementation support to organize public assessment of service delivery programme in all 33 provincial municipalities

2 planning workshops and 2 weeks of implementation support to design and cost selected service delivery programme in all 33 provincial municipalities

 4 weeks of implementation support to assist in launch and operation of new service delivery programme all 33 provincial municipalities

1 planning workshop and 1 week of implementation support to organize public assessment of service delivery programme all 33 provincial municipalities

All 33 provincial municipalities are implementing at least one new municipal service which covers the majority of municipal districts and which is planned and evaluated in partnership with the municipal populace

IDLG FP

GDMA

IDLG FP

GDMA

IDLG FP

GDMA

IDLG FP

GDMA

External FP

N/A

External FP

N/A

External FP

N/A

External FP

N/A

Channel

Support

Channel

Support

Channel

Support

Channel

Support



Sub-output 5.5

Deliverable 1

2H 2012

Deliverable 2

1H 2013

Deliverable 3

2H 2013

Deliverable 4

1H 2014

Target

1H 2014

Implementation of improved organizational designs for Provincial municipalities

Development and approval of new Municipality structures and TORs of major units and positions based on consultative/participatory process

Workshop in all 34 provinces to adopt/select new Municipality structures

Approval of new structures and incorporation into IDLG administrative arrangements for all 33 Provincial Municipalities

Workshop and two weeks of implementation support to implement new TORs, budget structures reporting lines for all 33 Provincial Municipalities

All 33 provincial municipalities have implemented new organizational designs incorporating a degree of flexibility in respect of staffing levels and sub-structures, using a participatory design process

IDLG FP

GDMA

IDLG FP

GDMA

IDLG FP

GDMA

IDLG FP

GDMA

External FP

CSC

External FP

N/A

External FP

CSC

External FP

N/A

Channel

PAR 

Channel

Support

Channel

PAR 

Channel

Support

Sub-output 5.6

Deliverable 1

2H 2012

Deliverable 2

2H 2012

Deliverable 3

1H 2013

Deliverable 4

1H 2013

Target

1H 2013

Provision of selected equipment and furnishings for Provincial Municipalities (NPP sub-component 15, deliverables 15.1 and 15.2)

Assignment of resource envelope for upgrades

 Workshop in each Provincial Municipality to plan spending

 Implementation of upgrade by all 33 Provincial Municipalities

Reimbursement of Municipalities according to agreed spending plan and resource envelope

All 33 provincial municipalities have planned, financed and implemented a programme of selected upgrades to their internal offices and facilities

IDLG FP

 GDMA

IDLG FP

GDMA

IDLG FP

GDMA

IDLG FP

GDMA

External FP

 N/A

External FP

N/A

External FP

 N/A

External FP

 N/A

Channel

Investment

Channel

Support

Channel

 Investment